(Bismarck, ND) — The North Dakota State Lab that’s been under construction since 2024 is nearly complete. A project manager says crews are completing labs on the second and third floors and finishing a mechanical room. He said the state of the art building installed ductwork that is, “so wide you could almost drive a car through it.” More than 90-thousand tests will be conducted in the building each year once it’s complete. Construction is expected to be done in April and the state is expected to start moving in equipment in May.
North Dakota State Lab Nearly Complete