(Brookings, SD) — The Brookings County Planning and Zoning Commission still has questions regarding a new proposed powerline. The 765kV line will be the largest electric line in the upper midwest once it’s complete. Kevin Coss of Xcel Energy says it’s part of a multi-billion-dollar energy project to supply support to a grid that has to be able to move 10-thousand megawatts of capacity for the next several decades. The county commission says the only power they have over the project is regarding setbacks, and landowners are sending in requests. Deuel County has a two-thousand-foot setback, while Grant County has recommended a one-thousand-foot setback. Xcel said in a letter to Brookings County that any setback greater than 50 feet would increase the length of the transmission line.